Modular Changing Places Gantt Chart

10-Week Build Programme

A typical build programme for our most popular product, the CP Pod, is ten-weeks. This includes lead times for all materials and specialist equipment. 

Order Materials (Weeks 1-5). Whilst we hold most build materials in stock, we allow a 4-5 week lead time for steel frame fabrication, as well as the delivery of specialist equipment and any bespoke items.

Manufacture Pod (Weeks 5-9).  This captures everything, includingthe initial floor, wall and roof installation; insulation and cladding; first and second-fix electrics, plumbing and joinery; plus the installation and testing of all specialist equipment.

Groundworks (Weeks 8-9). If required, we prepare your site, including any demolition works and waste removal. We dig-out, prepare service runs, install the most suitable foundation system (concrete slab, pad system, groundscrews etc.); and complete any external finishing works.

Delivery & Installation (Week 10). On the final week, we deliver and install your fully complete pod. Services are connected and everything is then thoroughly tested and commissioned, ready to handover. 

Please note that a typical build programme for our larger units (CP+2 and CP+3 Pods) spans between 12-14-weeks in total.

We’ve recently completed a number of modular CP Pods. Get in touch to learn more.

Realtime Updates

All of our clients receive read-only access to our project management tool. This includes a live build programme, updated by your project manager, which enables you to track the progress of your modular Changing Places toilet in real-time.

Our Typical Approach

1. Design

We review your site and your objectives, then advise on the most appropriate options, services requirements and foundation system for your modular Changing Places. A breakdown of all associated costs is included.

2. Specification

Choose from a range of internal and external materials and options to finalise your specification (view full list of options here). If required, we will then submit and manage a planning application on your behalf (and build warrant application for any Scottish clients). 

3. Manufacture

Once we have formal permission to build and have agreed a start date with you, we start manufacturing your CP Pod at our Doncaster premises. We provide regular photo and video updates, as well as access to a live online build programme.

4. Groundworks

As your pod is nearing completion, we commence groundworks onsite, a couple of weeks prior to delivery. We prepare all services (upgrading them where necessary) and install the most suitable foundation system for your site.

5. Installation

Your pod is delivered and craned into position onsite as a complete unit, which is overseen by your dedicated project manager. Services are commissioned, ground is made good, we agree abd complete any final snags, then handover your new Changing Places facility.

6. Aftercare

Upon completion, we issue your O&M manual, complete with building certificates. We register your facility with the CP Consortium on your behalf, deliver specialist training to any relevant employees, and schedule future maintenance.

Why not download our modular CP brochure?

Recent Modular Projects

Rutland Water is now open to more disabled people and their families, after two Changing Places pods were installed by RISE
New Changing Places in Bromley! RISE install 2 new Changing Places as part of a scheme designed to open local parks to disabled people.
Rochdale AFC can now serve fans, and its local community, even better thanks to a brand new Changing Places from RISE Adaptations.
The last of 4 installations in the Boston area, RISE are proud to unveil its latest modular Changing Places toilet at Wide Bargate.

Get in Touch

07729 224 738
hello@riseadapt.co.uk

Send us a quick message via the form below and a member of the RISE team will be in contact a.s.a.p…

Download Product Info

Please submit your details to receive further information about our Changing Places facilities…

Don’t forget to check your ‘junk’ folder if you don’t immediately receive your download.

Changing Places Download
Changing Places
About Us

Call 07729 224 738 or email hello@riseadapt.co.uk
We’re open Monday to Friday, 08:00-18:00.

To learn more about Changing Places, why not download our brochure or attend one of our monthly online seminars.

Call: 07729 224 738
email: hello@riseadapt.co.uk
08:00-18:00, Mon-Fri

To learn more about Changing Places, why not download our brochure or attend one of our monthly online seminars.

Download Product Sheet

Please submit your details to receive further information about our modular home extensions…

Don’t forget to check your ‘junk’ folder if you don’t immediately receive your download.

Home Adaptations Product Sheet

Download Product Sheet

Please submit your details to receive further information about our sensory rooms…

Don’t forget to check your ‘junk’ folder if you don’t immediately receive your download.

Sensory Rooms Product Sheet